 |
| Concrete
Floors |
| |
| In
concrete screeded floors, the screed acts to diffuse the heat
across the surface providing an even temperature at the floor
surface.
Depending on the type of building, construction, standards,
there are a number of methods of laying the underfloor heating
pipes in concrete floor structures.
|
 |
 |
|
| The most popular method of installation
is as follows:
a. A concrete slab (or suspended beam and block
construction) is laid over a damp proof membrane.
b. A 20mm thick piece of insulation is fixed to the perimeter (external)
walls, to a height to include the depth of floor insulation and
screed. Whilst the edging insulation may be on show it is covered
by wall plastering and skirting boards.
c. Floor insulation laid to the whole area, joints are taped to
prevent the ingress of screed between the insulation boards.
The floor is now ready for the underfloor
heating pipework installation.
|
| |
| |
 |
 |
We
recommend you use a 50mm layer of Polyurethane insulation. If
there is not enough space for 50mm insulation, 25mm is recommended.
We recommend Polyurethane as it out performs polystyrene and
its greater density allows use of clip fittings. |
|
| |
If
you use polystyrene insulation (50mm) it is recommended that
you install wire mesh on top of the insulation and tie the pipe
to the mesh.
For other floor constructions please contact our technical department.
|
 |
 |
|
| |
| Please note some insulation manufactures
require additional separating membranes, please contact your chosen
supplier for advice.
The pipe is laid at 200-300mm centres dependent
upon design.
Care must be taken to protect the pipework
whilst installing the screed.
|
| |
| |
| Finally the floor finish is laid. Underfloor heating
works well with almost any floor finish; tiles, carpets (use carpets
with a resistance of less than 0.15 m2K/W), timber floors, plastic
etc. |
| |
| |
| The floor coverings and the adhesive must be suitable
for the temperatures that underfloor heating will provide, the maximum
temperature they need to resist is 40°C. Always check with the
manufacturer of the floor covering if it can be used for underfloor
heating. Timber floors need to have a moisture content below 10% to
avoid shrinkage. The system must be operated for 21 days with a very
low temperature to dry the screed, then the floor covering can be
laid. |
| |
| |
 |
| |
 |
| |